Progress 12/7/2016

As you can see, we’ve made some progress since the last time I posted. To us it seems things drag along, never going as fast as we’d like. We had hoped to be done by now, but that is not even close to happening! Shooting for early Spring now.

img_2253
All the exterior doors are installed and the chimneys have been framed in.
img_2255
Rear view with all the doors and windows installed. All those shavings are from the beams that had to be planed because of mold.
img_2349
All the siding waiting patiently to be installed.
img_2248
These are some of the colors/textures that will be on the outside/inside of the house. Includes cement siding from James Hardie (both here are painted BM Caliente {will be on the tower exterior} and Parrot Green {outside trim color}), the bark siding will be on the front top bump out & garage, and the weathered barn board will be on the walls in the tower, along with the pine beams.
img_2380
We got our 1000 gallon propane tank installed.
img_2411
Insulation work in progress, almost totally complete now.
img_2422
Starting to drywall the Master Bedroom – only partial because we are waiting to get an inspection.
img_2426
First layer of the shower pans are in. Next comes the rubber membrane and then another layer of cement/sand mix to have the correct slope to the drain.
img_2430
Current view into the Great Room.

 

img_2431
Foyer progress. Powder room in the room right next to the stairs.
img_2449
Electric panels. Lots going on here!
img_2450
Gas lines installed!
img_2444
We have heat! The first of two furnaces is installed and running on propane until we get the heat pumps installed and the vents in the roof.
img_2453
Decorative corbels stained for the exterior of the house.
img_2456
Window in the tower stained with a custom mix to look weathered and will hopefully match the barn board that will be installed on the walls. We built a platform about half-way up so that the beams, insulation and ceiling could be installed. Made it much easier, except for the part of getting up the stairs!
img_2463
View into Carrick’s room from the loft area. On the right will be where the 2nd furnace goes. He’s excited that he won’t have to be cold in the winter anymore or cook in the Summer.
img_2464
Insulation and the beams all installed in Cole’s bedroom ceiling.

Next on our agenda is

  • to finish up the shower pans
  • get the roof vents in (today)
  • get electric and plumbing inspected (hopefully this week)
  • work on drywall
  • get septic installed (next week)
  • get water run to the house (next week)
  • start tiling bathrooms and floors
  • about a million other things!

Thanks for checking in to see our progress. I’ll try to update more often as there will be more of the “finishes” going in.

 

Progress 07/01/2016

IMG_1621
Radiant floor heating in the basement
IMG_1635
Lots of late nights working ’til Midnight
IMG_1629
More basement in floor heating
IMG_1625
Mark’s beautiful piers
IMG_1651
Making sure it’s straight and level
IMG_1671
Windows are in and porch roof is up!
IMG_1678
Wink putting up the trusses on the porch
IMG_1675
Front and side — porch will be constructed next
IMG_1699
View of porch from the driveway
IMG_1706
Roof completed on the porch and shingles ready to go on
IMG_1708
Back-filling has begun
group pig roast
Pig Roast #24 crew

Lots of progress since the last update! The house is totally under roof now and some of the windows have been installed. The past couple of weeks were a blur because we were under deadline to get the in-floor heating installed each night after parts of the concrete floors were poured in the basement. We had three consecutive nights where we worked until after Midnight to complete the job. But we made it, and the basement floor is complete.

Our crew was also scheduled to complete their job for our builder (Hearthstone), but they agreed to stay and help us finish up some of the harder items on our list, like installing the windows and the timberframe roof on the porch. We had some hiccups getting the lift here and work slowed a bit, but we caught up. The porch is built, the roof is on, windows got installed and back-filling has started.

Our crew has to go to Virginia for a job, but then they’ll be back to finish up the windows and redo our tower roof. The original trusses were wrong, so they will be replaced to make the tower as tall as it should be!

We got a much-needed break this past weekend during our 24th annual Pig Roast held in Corry, PA to celebrate our 23rd wedding anniversary. Just look at the wonderful group that was there!

We’ll now put our attention to the shingle installation, final siding choices, porch construction, interior walls, electric installation to the house and a million other things! Thanks for checking in!