Progress 2/23/2016

img_2641
Beautiful sunset from the hill. The weather this winter hasn’t been that bad. The only problem has been with the freeze/thaw cycle and making the whole work site a sticky mudhole. The past week has dried it out though, thank goodness!
img_2630
We moved on the the tower ceiling after the drywall on the 1st floor. We built a platform up in the tower to be able to reach the ceiling without being on ladders. Made life a whole lot easier! The plan is to put reclaimed barnwood on the walls in the tower after the drywall is done elsewhere.
img_2633
The completed Master Bath waiting for the next phase of drywall mud and tiling.
img_2627
After the tower and bath, we moved on the ceiling in the Mast Bedroom. This was a little easier because we had more straight shots and not as many angles.
img_2643
Each piece was cut to fit in the cavity between the beams, so that it could slide in. Some cuts had to be made for lags that hold the heavy timbers up and lights and vents.
img_2646
And here is the completed ceiling!
img_2655
Next we moved up to the second floor and the boys’ bedrooms. This took about a week of nights and weekend to complete. It went pretty quick once we got the hang of it. The only hang ups here were the cuts for wiring, lags and pipes.
img_2654
Now we’ve moved on the dry walling the 2nd floor. It can be tricky trying to get the long sheets of drywall up the stairs!
img_2657
Cole’s bedroom
img_2658
Cade’s bedroom.

For now, we’ll be finishing up the drywall on the second floor. That will take a little more figuring because Mark has to build little walls at the top of the big walls so that they touch the ceiling and we can attach the drywall.

Since the weather has been so nice, we even started working on the outside —installing some of the soffit and siding.

Most of the electrical work is done. We even have some switches and outlets so that we don’t have to run so many extension cords!

I will most likely start the tiling soon. I’ve ordered a lot of the tile and there is a lot to do!

Advertisements

Progress 01/09/2017

Even though the weather has been really cold, we’ve gotten a lot done over Christmas break. A lot of drywall has gone in and most of the first floor is almost ready for taping and mudding. Thank goodness for heat. We keep it around 55 degrees most of the time.

I’m glad that it has been cold for a while, because when it warms up the driveway turns to very slippery, greasy mud. I think that we are in store for that again this week. Can’t have everything!

img_2477
The well is hooked up. We had some issues there, but hopefully they are all resolved.
img_2481
The Master shower is ready for tiling. The floor pan is done by hand in 2 steps. I know the shower is huge, but the space would have been tiny and wasted in the Master closet, so I added it to the shower. Most likely it will be done in large format subway tile with accents and honed marble floor.

 

img_2484
Carrick’s shower is also complete and ready for tiling. Cade’s is almost identical, but Cole asked for a bathtub in his.
img_2500
The kitchen part way through dry walling.
img_2525
The kitchen even further along. The area that has the grey backerboard is where the range will be. That area will be tiled and a hood will be installed.

 

img_2532
Here is Mark working on the pocket door between the Laundry/Pantry room and Kitchen.

 

img_2522
Mark installing drywall in the Dining Room.

 

img_2504
View from the Great Room into the Dining Room and Kitchen.

 

img_2558
View of the Kitchen with all the drywall complete.

 

img_2559
Another view of the Kitchen with a view of the pocket door hardware installed. The door beside the opening is the one that will be installed there. The other area to the right is the Mudroom. The flooring throughout this area will be a dark gray slate. This area, along with the Dining Room and part of the Foyer will have drywall ceilings for a change over the pine board that will be in the other parts of the house.
img_2586
And now I am working on putting all the cabinets together that I purchased at IKEA almost 2 years ago! Who knew it would take so long to get this far! It has been a little difficult because the final room sizes didn’t end up being the exact same as the plans. That means I have to make some adjustments and move some around. All of the cabinet doors will be painted. The cabinets around the perimeter of the Kitchen will be Linen from Amy Howard Paints. The Island in the Kitchen will be painted Eulalie’s Sky and the Pantry will be Luckett’s Green from Miss Mustard Seed.
mm-paint
Miss Mustard Seed Paints – Eulalie’s Sky (Island) and Luckett’s Green (Pantry).
ah-paint
Amy Howard Paints

 

Next up is

  • Finishing cabinet construction. Pantry is almost done and Kitchen is partly done.
  • Install cabinets.
  • Finish drywall in the Master Bedroom and Foyer.
  • Start taping and mudding and sanding (I HATE this part).
  • Begin tile work.
  • Decide on tile for all the boys’ baths (that ought to be interesting).
  • Decide on flooring. This has been a real struggle for me.
  • Get the other heating system installed upstairs when our HVAC guy isn’t on Emergency Call! This weather has kept him busy, but we aren’t in a hurry.
  • Finish the wood staining in the Great Room (windows) and seal.

Save

Save

Save

Progress 12/7/2016

As you can see, we’ve made some progress since the last time I posted. To us it seems things drag along, never going as fast as we’d like. We had hoped to be done by now, but that is not even close to happening! Shooting for early Spring now.

img_2253
All the exterior doors are installed and the chimneys have been framed in.
img_2255
Rear view with all the doors and windows installed. All those shavings are from the beams that had to be planed because of mold.
img_2349
All the siding waiting patiently to be installed.
img_2248
These are some of the colors/textures that will be on the outside/inside of the house. Includes cement siding from James Hardie (both here are painted BM Caliente {will be on the tower exterior} and Parrot Green {outside trim color}), the bark siding will be on the front top bump out & garage, and the weathered barn board will be on the walls in the tower, along with the pine beams.
img_2380
We got our 1000 gallon propane tank installed.
img_2411
Insulation work in progress, almost totally complete now.
img_2422
Starting to drywall the Master Bedroom – only partial because we are waiting to get an inspection.
img_2426
First layer of the shower pans are in. Next comes the rubber membrane and then another layer of cement/sand mix to have the correct slope to the drain.
img_2430
Current view into the Great Room.

 

img_2431
Foyer progress. Powder room in the room right next to the stairs.
img_2449
Electric panels. Lots going on here!
img_2450
Gas lines installed!
img_2444
We have heat! The first of two furnaces is installed and running on propane until we get the heat pumps installed and the vents in the roof.
img_2453
Decorative corbels stained for the exterior of the house.
img_2456
Window in the tower stained with a custom mix to look weathered and will hopefully match the barn board that will be installed on the walls. We built a platform about half-way up so that the beams, insulation and ceiling could be installed. Made it much easier, except for the part of getting up the stairs!
img_2463
View into Carrick’s room from the loft area. On the right will be where the 2nd furnace goes. He’s excited that he won’t have to be cold in the winter anymore or cook in the Summer.
img_2464
Insulation and the beams all installed in Cole’s bedroom ceiling.

Next on our agenda is

  • to finish up the shower pans
  • get the roof vents in (today)
  • get electric and plumbing inspected (hopefully this week)
  • work on drywall
  • get septic installed (next week)
  • get water run to the house (next week)
  • start tiling bathrooms and floors
  • about a million other things!

Thanks for checking in to see our progress. I’ll try to update more often as there will be more of the “finishes” going in.

 

Progress – 10/26/2016

OK, so it’s been two months since I updated! Things got hectic with back to school and everything that goes along with carting 3 boys around to all their events.

Steady progress has been made since the last time I checked in. The roof is on most of the house (with the exception of where the chimneys will go), all the doors are installed, the electric and plumbing are almost complete, large beams were installed in the Master Bedroom, and a whole bunch of other smaller jobs were completed. We are looking forward to our first inspection soon!

Here is the visual tour:

IMG_2104.JPG
View of the house with the roof completed. (09/13/16)
IMG_2197.JPG
The fireplace going in. Since all of our fireplaces are propane, they just need to be plywood boxes that we will apply the stone to. (10/4/16)
IMG_2205.JPG
Large pine beams in the Master Bedroom and Bath – completed. (10/4/16)
IMG_2146.JPG
Mark installing the beams. We had to use a pulley system with straps to get the very heavy beams in place. (9/25/16)
IMG_2207.JPG
My bath tub installed in the bath. It is a wonder that it survived in one piece for as long as it has been sitting around the work site! (10/4/16)
IMG_2209.JPG
Electric and heating going in the basement. (10/6/16)
IMG_2228.JPG
Mudroom door installed.(10/16/16)
IMG_2229.JPG
French doors to the screened in porch. These doors are 96″ tall. The open spot to the right of the doors will be a fireplace, and there will also be one on the porch.
IMG_2233.JPG
Front door installed! (10/16/16)
IMG_2216.JPG
Timber roof over the window in the basement. These will be covered with metal roofing. (10/10/16)

 

IMG_2179.JPG
This is what happened to some of our beams during storage while we were constructing our house. Because they were wet, mildew grew on the beams. I tried about 15 different things to remove it, but nothing worked. Bleach was the only thing that removed it somewhat, but still not enough.
After a lot of research, Mark decided to purchase an electric planer. Even though it was expensive, it did the job much quicker and better than the previous attempts. No more black and hours of sanding/treating. (10/23/16)
IMG_2255.JPG
Shot of the rear of the house. You can see the huge pile of shavings left behind after we planed some of the beams. Also note that the La Cantina door has been installed.

Next up on the schedule is getting the siding and soffit installed, insulation in the ceilings and partial basement walls, beams on the second floor ceiling, finishing up the HVAC so we can work in a warmer area since the weather has turned colder, painting the cabinet doors for the kitchen/pantry, installing the septic, gas and water, and about a thousand other things! I hope that the weather doesn’t turn too cold for a while.

IMG_2149.JPG
And a big shout out to this guy for all the help he gives us. We couldn’t get as much as we do without his help.

Thanks for checking in!

Save

Save

Progress 7/25/2016

IMG_1745
Interior Framing, looking into Master Bedroom

We started the framing of the first floor last weekend. It went relatively quickly, except for all the extra figuring with the vaulted ceilings. We got all the framing completed there and then moved on to the stairs.

IMG_1746
Interior Framing – looking from Dining into Kitchen

 

IMG_1747
Interior Framing – Master Bedroom, closet and bath
IMG_1749
Electric Service, waiting for hookup

It was interesting to get the wires from the house to the pole so that our house can be hooked up for service. It took about 250 ft. of large electric cable and a lot of horsepower to get the cables pulled through the pipe. The cable was slowly pulled through the pipe with a lot of pipe lube and the cable attached to a rope, which was then attached to the truck. Everything was hooked up on our end and inspected. Now we just have to wait until Dusquesne Light comes to hook it up to their system. Hopefully soon! It stinks to have to run everything off of a generator.

This past weekend we worked on framing the stairs, which took a bunch of figuring! None of the sets of plans we had were the same, so Mark had to figure out all the measurements, build the walls, and cut all the stringers. I have to say he did a really good job! Everything worked as he thought it would.

IMG_1763
Second floor framing

Now we are moving on to the 2nd floor framing of the boys’ bedrooms and bathrooms. This is also time-consuming because of the vaulted ceilings here, along with beams that will be installed later.

IMG_1764
Stairway to second floor

I realized that I didn’t take a photo of the stairs from the 1st floor, so I’ll have to do that.

IMG_1770
Trying to keep the rain out during the storm

It wasn’t too long into the afternoon yesterday when it began to storm. We could still keep working, but it is hard because the roofing is not on yet and it leaks like a sieve!

Hopefully the roof will be put on soon. We’re just waiting on special order drip-edge (my fault — I wanted galvanized like the gutters).

IMG_1773
The valley during the rain storm
IMG_1774
2nd Floor framing of the boys’ bedrooms and baths

IMG_1775IMG_1776

Our crew is supposed to return this week, so hopefully we can get the roof on the front porch and all the windows installed, along with the new roof on the tower.

I’m still waiting on the bid for the siding and gutters, so after the roof is on we’ll move to buttoning up the outside so we can get working on the interior finishes.

I’ve completed finishing one set of doors to the porch and have 1/2 of the front door completed (stained and finished). It takes a while since there are so many steps to getting them done. I’ll have to remember to snap a photo of them.

Progress hasn’t been as fast the past two weeks because Mark started a new job and he’s still learning the ropes and going to training. But I think that we still have done pretty well.

Thanks for checking in!