Progress 07/01/2016

IMG_1621
Radiant floor heating in the basement
IMG_1635
Lots of late nights working ’til Midnight
IMG_1629
More basement in floor heating
IMG_1625
Mark’s beautiful piers
IMG_1651
Making sure it’s straight and level
IMG_1671
Windows are in and porch roof is up!
IMG_1678
Wink putting up the trusses on the porch
IMG_1675
Front and side — porch will be constructed next
IMG_1699
View of porch from the driveway
IMG_1706
Roof completed on the porch and shingles ready to go on
IMG_1708
Back-filling has begun
group pig roast
Pig Roast #24 crew

Lots of progress since the last update! The house is totally under roof now and some of the windows have been installed. The past couple of weeks were a blur because we were under deadline to get the in-floor heating installed each night after parts of the concrete floors were poured in the basement. We had three consecutive nights where we worked until after Midnight to complete the job. But we made it, and the basement floor is complete.

Our crew was also scheduled to complete their job for our builder (Hearthstone), but they agreed to stay and help us finish up some of the harder items on our list, like installing the windows and the timberframe roof on the porch. We had some hiccups getting the lift here and work slowed a bit, but we caught up. The porch is built, the roof is on, windows got installed and back-filling has started.

Our crew has to go to Virginia for a job, but then they’ll be back to finish up the windows and redo our tower roof. The original trusses were wrong, so they will be replaced to make the tower as tall as it should be!

We got a much-needed break this past weekend during our 24th annual Pig Roast held in Corry, PA to celebrate our 23rd wedding anniversary. Just look at the wonderful group that was there!

We’ll now put our attention to the shingle installation, final siding choices, porch construction, interior walls, electric installation to the house and a million other things! Thanks for checking in!

Advertisements

Progress 6/14/2016

IMG_1568
Progress on the Great Room
IMG_1573
Great Room Ceiling
IMG_1576
Master Bedroom trusses
IMG_1552
Pouring concrete for the porch footing
IMG_1577
Working on laying block for the porch piers
IMG_1579
Porch piers progress

The past two weeks seem to have been a blur at the job site. More of the roof was completed and the crew is getting to the end of their part of the job. Right now they are working on completing the roof over the Master Bedroom/Bath and the Tower stair area. We have been working on the piers for the screened in porch and getting the basement ready for the rest of the concrete flooring, which will start tomorrow. We are also waiting for our plumbing and footing inspections that will take place tomorrow.

Next up after that is getting the roofing on and the windows installed, along with back-filling the foundation so that we can have a weather-tight shell to get moving on the inside work.

Progress 05/31/2016

IMG_1514
Front view of the house
IMG_1512
Side view of the house
IMG_1519
Inside view of second floor
IMG_1524
Side view at back
IMG_1528
Back view

As you can see, things have really been moving along! In the past week and a half they got the 2nd floor up and many of the roof rafters. This week I think most of the roof will be up and covered. The great room (shown in the photo above) will be more time consuming I think because it is all heavy timber rafters.

Over the Memorial Day weekend Mark, Carrick and I worked on finishing up the skirting around the first floor trusses, removing the forms from the last concrete pour, screeding and removing extra gravel from the basement to get more area ready for the next pour and just generally cleaning up the work site (which the crew keeps pretty clean). We also took time to honor those who gave the ultimate sacrifice for our freedom (Cade & Cole marched in the Freedom and Conway Memorial Day Parades).

IMG_1545
Waiting in Conway to start the parade.

Our next steps are the get the footing poured for the porch supports, estimate the huge amount of stone we need to order, and get the house under roof so windows can be installed. All of my doors came in and it took me a while to finally decide on stain color. I also have all my appliances. The last purchase was the hood and blower for the stove that I bought on eBay. I will be glad to get all of these things installed that we have been storing for over a year!

How we got here

timberlake201
Bob Timberlake Studio – Hearthstone

I thought I should tell the story of how we got started on our house journey many years ago. While living in the Chicagoland area, Mark and I decided we wanted to build a house since we couldn’t find anything that we liked. After looking at a lot of plans, we came to like this one from Hearthstone, but the actual building never took place because we couldn’t find land cheap enough and we also wanted to move back to the Pittsburgh area.

When we moved back, my dad found us an old farm on 24 acres that had an old house on it and we thought we’d fix it up and just live there while we were building the new house. Too bad it didn’t work out that way! The old house needed a total overhaul that took 10 years to finish. So now we were finally ready to start.

I started looking at log homes companies again and I still liked what Hearthstone had to offer. I found a series of plans that they had from MossCreek. That lead me to look at their selections in depth and I found “The Wedge”.

Wedge-Main
© 2016 MossCreek

By total coincidence, found out that their offices were located in Knoxville, TN and I was going to be there for one of the twins’ competitions. I met with them and talked about what we wanted in our design. After that, we decided to go with “The Wedge” and started to make changes to the stock plan to reflect how we wanted the layout. I changed the location of the screened in porch, along with no longer splitting up the laundry room and pantry (now one room). I’ll show you that in the future.

wedgem
The Wedge Main Floor

After deciding on the plan, we had to finalize what builder we were going to use. After looking at several and going over costs, we decided on Hearthstone because they we willing to work with us to keep cost down and we also now had decided that we didn’t want a totally log home. Neither of us like the “heavy wood” look, and decided only to use log veneer in the Great Room. Other parts of the house will have reclaimed wood and drywall, and the Great Room will also have large wooden scissor trusses.

O:HOMES BY MOSSCREEKHBM63-00 WEDGEHBM63-01 WEDGE-SKUSEHBM630
First Floor Plan – Skuse Wedge

Here is what the plan looks like after we make our changes. I took a lot of time and thought into what would work best for our family. I got the idea for the combo pantry/laundry from Better Homes and Gardens last year. It was a lot of back and forth, but I think that we got it right!

Progress – 05/12/2016

IMG_1368
Front of the house
IMG_1372
Rear of the house — Master Bedroom
IMG_1374
Front Porch area/Kitchen
IMG_1377
Master Bedroom Interior
IMG_1393
Mark in the Kitchen

We’ve been really lucky this week weather-wise. Most of the rain predicted for us went right around the site! More of the panels went up in the stair tower area and bracing was put in for the windows and doors. Interior load-bearing walls are also going in. I don’t think it has progressed as quickly as the crew would like since they had told us they’d be done this week. There is still another whole floor and all the roof to put on, along with the porch and some of the windows. But progress is progress!

I will write in my next post about how we got started on our housebuilding journey. And don’t be a stranger, I’d love to hear what you think — leave a comment!

Progress – 05/06/16

IMG_1340
Progress Wednesday evening
IMG_1344
Progress on Thursday
IMG_1345
The side/back view
IMG_1351
Friday Progress – Great Room
IMG_1353
Friday Progress – the Master Bedroom and Bath

We’ve had quite a bit of rain this past week, so progress is slow. We’re also waiting for more truckloads of house parts, due to arrive on Tuesday. They have walls up on the first floor and just have the large great room window section and the stairwell section to go before they move onto to 2nd floor. They think they’ll be done this week, but I am not as optimistic. There is rain in the forecast everyday this week.

We worked this weekend on one of the wall corners Mark wasn’t happy with, installed OSB on the back part of the walkout basement and part of the skirting where the trusses meet the floor and 1st floor. He also installed the strongbacks in the trusses in the basement. It was pretty nice weather-wise, but I have a bunch of new splinters in my hands.

 

Work Continues

IMG_1333
SIP panels going up for kitchen and dining room

The crew got some of the panels set yesterday and it is beginning to take shape. All of the exterior walls are constructed of SIP panels so it should go pretty fast. Our construction is known as a “Hybrid home” made out of SIPs, trusses, large wooden beam trusses (in the great room) and conventional interior construction. We went this route because of cost and energy efficiency. We didn’t want a total log home so we will have log veneer in the great room, weathered wood in the stairwell tower and a mix of drywall/wood in the rest of the house. Our home provider is Hearthstone Inc. out of Tennessee. We’ve been working with them for years on trying to get just what we want.

IMG_1334
corner of the side/front of the house

 

IMG_1336
Supplies
IMG_1337
Front of the house: mudroom, pantry/laundry
IMG_1338
The crane that lifts the panels in place
IMG_1339
Checking out the windows

The Reps came today from Andersen and Home Depot to check the windows for any damage that happened during shipment. So far there was only one window that had a little damage that can be fixed, but nothing major like a broken window. They stand behind their product and if we find any issues down the road, they will fix them. So hopefully that will put that out of the panic mode for now. We had to rent a 40′ trailer to store all the windows in until installation! We thought there’d be room for other items as well, but that really isn’t the case. We have a garage full of doors, appliances, cabinets and furniture down at our current house and our basement is FULL of all the lighting, plumbing fixtures, rugs, and other treasures I have found in the past two years we’ve been waiting to build! At least that gave me lots of time to find bargains — I’ll share my secrets on that in a future post.

For now, the weather is holding. Hopefully we won’t get too much rain over the next week while they are putting the house together. We just got another truck in this morning with more panels and more supplies are set to come in soon.

Thanks for checking in!

Getting there!

It’s been a little while since I last posted, but we’re getting somewhere now. I didn’t have time to update because we have been very busy finishing up our end of the work before our building crew came in with the actual top two stories of our house. I was also in Atlanta for 5 days with the twins for their National Academic Games competition.

IMG_0180
Having fun at the World of Coca-Cola

Let me show you the progress:

IMG_1166
First inspection passes – plumbing under slab
IMG_1178
Getting the trusses in
IMG_0181
Pouring the concrete for the basement
IMG_1306
Progress on the walkout
IMG_1309
The elevator shaft…er, stairwell
IMG_1312
Looking out of the basement
IMG_1320
Getting closer to completion
IMG_1326
Final touches and the crew starts!

 

We have a few smaller jobs to finish up for the crew, like build a support wall and install some support piers for out screened in porch off the side (near where the dirt bike is in the photo above), but we are getting there. If the weather would just cooperate and keep warm and dry we’d be great. That will be tonight’s job.

Next up for us is that tomorrow the Andersen rep is coming to check out all 40+ of our windows that we had issues with on delivery. We ordered them from Home Depot and they were unfortunately delivered by people that had no business delivering them, so they all need checked before installation for damage! Ugh. And there are some huge windows, some 10’+ tall! Hopefully it will all turn out well. It is just disheartening because we took our time with the order to make sure that they were exactly right before placing the order and now this happens.

Progress!

IMG_1160
Duquesne Light installing a new pole in the front yard of our current house

After waiting for over 2 months after FULL payment, our electric service is finally starting to be put in. Since our neighbor wouldn’t agree to let us come off the pole right across the road, we had do sign a new Right-of -way agreement and now we have 2 more poles in our yards. Not the best placement, but better than nothing! We have another pole on the other side of our new driveway for any electric we want at the bottom of the driveway, like lights or a gate mechanism. Most of the lines will be underground.

IMG_1161
other electric pole and our new driveway

Our plumber is also here today to put in the waste lines for the basement before we pour part of the concrete floor. Then inspection has to be scheduled for Monday.

And not to be left out, we also got a gravel delivery in the middle of all of this activity.

I won’t keep y’all in too much suspense about what the house will look like… here is the original plan we started with: The Wedge from MossCreek.

Wedge-Main
© 2016 MossCreek

 

In one of my next posts, I’ll let you know a little more about it and the process we went through to get the exact layout we wanted.

Come along on an adventure…

…join us for an adventure in homebuilding! It’s been a long time in the making, but we are finally on our way to creating our dream home in the hills of Western Pennsylvania.

I will be sharing our journey of contracting, building, selecting materials and making all the decisions that go into making a home.

For now I will leave you with a photo of the amazing view we have from our lot.

IMG_0895